Okay, now major work is taking place. I drove by at 10 this morning and there was not a lot done (as seen from the road), but when I drove by again at 12:30 they had a wall or two up in Emmy's room! Very exciting. Last week, the constuction crew had the flu. The main boss, Mark, did come out and put on the plywood floor by himself, but he couldn't do the big stuff alone. Last week was a wasted week.
Hendryx did come last week and they dug a big hole for the septic tank. They are there today also.
Also, as I drove by the second time today the geothermal guys were pulling in. They are going to hook up the system.
Sydney has ear infection, so I am not firing on all cylinders today. I think I will just stop now. I hope to get out there later today to take pictures of the day's progress.